Baosteel 3,2 MW waste heat recovery project
Shanghai, ChinaEnergy efficiency
Turn-key supply of a 3,2 MWe ORC in Waste Heat Recovery on an iron ore sintering plant in Baosteel steel mill in Baoshan, a suburb of Shanghai.
Organic Rankine Cycle Module Orchid© of 3,2 MW working with a refrigerant at 150°C pressurized water/159°C saturated steam and hydro-condenser
Project activities
Main company
ENERTIME
Activities
Equipment manufacturer
Type of implantation in the country
Office
Project Information
Detail of the equipment used
Organic Rankine Cycle Module Orchid© of 3,2 MW
Installed power (specify unit KW, MW or other)
3 200 kW
Annual produced energy (specify unit MWh or other)
24 GWh
Grid connection
On grid
Main fundings
Owner's funding
Project cost (in euros)
-
Year of entry into service
2017
Project progress
Employees mobilized
-
1
Locals employees
-
1
Employees for the development phase
-
4
Employees for the construction phase
-
1
Employees for maintenance
Main company
ENERTIME
- Waste recovery , Wood-Energy , Thermodynamic solar , Geothermal , Heat pumps , Ocean renewable energy
- Equipment manufacturer
- International ADEME Club membership